Spiral Steel pipe in the inspection process need to pay attention to matters

2017-08-07 08:52:20   COMMENT:0 HITS:
  Spiral Steel pipe in the inspection process need to pay attention to matters

  1, oiling marking: in the inspection of qualified spiral pipe oiling operation to prevent corrosion, and in accordance with the requirements of customers marking.

  2, flatten milling edge: the use of anvil machine will be the original curled steel plate leveling, and then through the milling machine on both sides of the steel plate for double-sided milling, to achieve the required plate width, parallel side of the board and groove shape.

  3, shear molding: the steel plate along the Large Diameter SSAW Spiral Welded Steel Pipe into a tube.

  4, butt welding: double-sided submerged arc welding technology for pre-welding, welding, welding. The welded steel pipe was cut into a standard length using a plasma scale.

  5, visual inspection: by the professional and technical personnel to check some of the basic parameters.

  6, ultrasonic testing: both inside and outside the weld and weld on both sides of the base metal 100% inspection.

  7, X-ray inspection: the inside and outside the weld 100% X-ray industrial TV inspection, the use of image processing system to ensure the sensitivity of testing.

  8, the pressure test: the hydraulic test machine on the steel pipe by root inspection to ensure that the steel pipe to meet the standard requirements of the test pressure.

  9, chamfering head: the inspection will be qualified after the spiral pipe pipe processing, to achieve the required pipe end groove size.

  10. Final inspection: re-ultrasonic and X-ray inspection and the end of the magnetic test, check the existence of welding problems and pipe terminal defects.